CITY COUNCIL AGENDA ITEM
ACTION REQUESTED:
title
Approve the award of Bid 24-007, 2024 Parking Lot and Multi-Use Path Maintenance, to Denler, Inc., for an amount not to exceed $1,142,370.43, plus a 3% contingency
body
DEPARTMENT: Transportation, Engineering and Development
SUBMITTED BY: William J. Novack, P.E., Director of Transportation, Engineering and Development/City Engineer
BOARD/COMMISSION REVIEW:
N/A
BACKGROUND:
In May 2024, the Transportation, Engineering and Development Business Group (TED) issued Bid 24-007 seeking contractors to perform maintenance and repairs on City-maintained parking lots and bike paths. This is a joint project involving TED, the Water Utilities and the Electric Utility. Maintenance required by these departments are combined into one project that will be managed by TED.
The 2024 project involves the maintenance of 38 City-owned parking lots, including:
• 3 downtown business district lots,
• 9 commuter lots,
• 1 police department lot,
• 4 fire stations,
• 1 public works lot,
• 2 park district lots,
• 1 library parking lot,
• 1 electric department site, and
• 16 sites maintained by the Water-Wastewater Utility.
In addition to the locations listed above, six sections of multi-use paths will also be maintained. The maintenance work will range from low-impact maintenance (crack sealing and parking stall painting) to high-impact maintenance (seal coating, patching, and resurfacing).
Restrictions were incorporated into the contract to minimize impact to residents, businesses, and visitors by maintaining appropriate access, decreasing the reductions in the number of parking spaces available, and limiting construction hours to off-peak periods. As part of the project, TED will communicate with City departments, as well as outside partners, including but not limited to the Downtown Naperville Alliance, adjacent business owners and commuters.
DISCUSSION:
Advertisement Date: |
05/03/2024 |
Notices Sent: |
229 |
Opening Date: |
05/22/2024 |
Planholders: |
21 |
|
|
Proposals Received: |
1 |
A bid was received from the following vendor:
Vendor Name |
Proposed Cost |
Engineer’s Estimate |
$1,484,154.62 |
Denler, Inc. |
$1,142,370.43 |
One bid was received for this project. The contractor has performed work on previous parking lot maintenance programs for the City and is currently working for the City as the contractor for the crackfill program. In 2020 and 2022, Denler was the sole bidder on the City’s Parking Lot Maintenance Program. This year we received one No Bid form that stated the contractor did not have enough references to meet the City’s requirements.
Staff recommends moving forward with the award to Denler as the lone bid is lower than the Engineer’s Estimate and approved budget for this project.
The completion date is October 18, 2024.
FISCAL IMPACT:
CIP #: MB035, MP016
The 2024 Parking Lot and Multi-use Path Maintenance project is expensed to the account numbers listed below. A combined total of $1,741,500 is included in the Capital Improvement Program for these projects in the 2024 Budget. Additionally, the Water Utilities included $27,000 for paving and stripping of the South Operations Cebter parking lot. The requested award, including the contingency, is within the budget.
Account Number |
Fund Description |
Total Budget |
30281200-551502 |
Commuter Parking Fund |
$499,500 |
30282200-551502 |
Capital Projects Fund |
$29,448,000 |
30284300-551502 |
Downtown Maintenance Fund |
$499,000 |
40251300-551502 |
Electric Utility Fund |
$15,179,200 |
41252000-551502 |
Water Capital Fund |
$40,264,902 |
41101500-531302 |
Water Utility Fund |
160,000 |
*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.