File #: 26-0007    Version: 1
Type: Procurement Award Status: Agenda Ready
File created: 1/2/2026 In control: City Council
On agenda: 1/20/2026 Final action:
Title: Approve the award of Bid 25-254, 2026 Saybrook Phase III Water Main Improvements, to Mauro Sewer Construction for an amount not to exceed $3,678,924.25, plus a 3% contingency, and for a 17-month term
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 25-254, 2026 Saybrook Phase III Water Main Improvements, to Mauro Sewer Construction for an amount not to exceed $3,678,924.25, plus a 3% contingency, and for a 17-month term

body

 

DEPARTMENT:                      Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

In support of the City’s priority to provide utility services that are reliable and safe, in November 2025, the Water Utilities issued Bid 25-254, 2025 Saybrook Phase III Water Main Improvements.  The project includes the replacement of the water main on the following streets in the Saybrook subdivision: 12th Avenue, Trefoil Court, Suffolk Street, Barley Avenue, Millet Street, Brainard Street, Loomis Street, Blue Grass Court, Sleight Street, Wright Street, and Case Street. 

 

The purpose of the project is to replace aging and deficient water main on these streets.  The existing four-inch and six-inch cast iron water main was installed in the 1960’s and will be replaced and upsized to eight-inch ductile iron pipe in accordance with City standards.

 

DISCUSSION:

 

Advertisement Date:

11/5/2025

Notices Sent:

1090

Opening Date:

12/19/2025

Planholders:

60

 

 

Proposals Received:

15

 

Bids were received from the following vendors:

 

Vendor Name

Base Bid

Bid Alternate A

Mauro Sewer Construction

$3,678,924.25

$3,497,688.25

Winninger Excavating, Inc.

$3,725,639.15

$3,492,821.15

Miller Pipeline LLC

$3,799,598.40

$3,771,725.37

J Congdon Sewer Service

$3,863,367.90

$3,648,427.90

Concept Plumbing, Inc.

$4,054,165.67

$3,973,406.50

Cerniglia Co.

$4,193,935.15

$3,942,262.30

Trine Construction Corporation

$4,255,100.00

$3,923,000.00

C Szabo Contracting

$4,261,755.00

$3,993,236.00

Engineer’s Estimate

$4,317,792.00

$3,614,317.00

Bluewater Construction LLC

$4,440,000.00

$4,265,062.00

A Lamp Concrete Contractors

$4,469,012.40

$4,218,970.40

Millennium Contracting Co.

$4,516,166.00

$4,256,542.00

Acqua Contractors Corp.

$4,600,000.00

$4,215,000.00

Performance Construction & Engineering

$4,819,871.40

$4,498,820.40

Gerardi Sewer and Water Co.

$5,396,263.50

$5,164,528.50

Martam Construction, Inc.

$5,776,222.35

$5,544,692.35

 

The bid documents for this project included a Base Bid to obtain pricing for ductile iron water main pipe and Bid Alternate A to obtain pricing for PVC water main pipe.  After evaluating the submitted bids, the department determined that selecting the lowest Base Bid was appropriate.  Ductile iron is the City’s standard water main material, and while PVC has been used in recent years due to substantial cost savings, the cost of ductile iron is once again competitive.

 

Mauro Sewer Construction submitted the lowest Base Bid for the project at $3,678,924.25. The low bid is 37% lower than the budgeted amount of $5,827,800. Water Utilities staff based the 2026 budget on the average per-foot cost it has been receiving for the last several years. 

 

Reference check indicates Mauro Sewer Construction to be capable contractors and

Staff recommends award of the contract to them as the lowest responsive and responsible bidder as defined by Section 1-9B-7 of the Procurement Code (RBO-qualified).

 

The substantial completion date for this project is October 31, 2026, with a final completion date of June 30, 2027.

 

FISCAL IMPACT:

CIP#: WU410 - Saybrook Phase III Water Main Improvements

 

Saybrook Phase III Water Main Improvements will be expensed to the Infrastructure account listed below. The 2026 Budget includes $6,177,468 for the completion of this project. The award amount, plus contingency, is favorable to the budget.

 

Account Number

Fund Description

Total Budget Amount

41251500-551502

Water Utility Fund

$86,910,285

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.