File #: 25-0160    Version: 1
Type: Procurement Award Status: Passed
File created: 1/31/2025 In control: City Council
On agenda: 2/18/2025 Final action: 2/18/2025
Title: Approve the award of Work Order 22-067-WATER-25-01, Construction Engineering Services for Ogden Avenue and Washington Street Water Main Improvements, to Ciorba Group for an amount not to exceed $268,828.59 and for a 22-month term
Related files: 25-0488

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Work Order 22-067-WATER-25-01, Construction Engineering Services for Ogden Avenue and Washington Street Water Main Improvements, to Ciorba Group for an amount not to exceed $268,828.59 and for a 22-month term

body

 

DEPARTMENT:                      Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

On April 5, 2022, City Council awarded RFQ 22-067, Engineering Consulting Services for Watermain and Sanitary Sewer Projects, to Baxter & Woodman, Ciorba Group, Civil & Environmental Consultants, Inc., Crawford, Murphy & Tilly Inc., and Fehr Graham. The shortlisted firms are available for watermain and sanitary sewer projects.

In March 2023, Water Utilities issued a quotation request for Work Order 22-067C seeking to retain the services of a qualified and experienced consultant to prepare construction drawings and technical specifications for the replacement of the water main on Ogden Avenue from Washington Street to Wright Street and Washington Street from Ogden Avenue to Bauer Road. 

 

Work Order 22-067C was issued to the consultants listed above.

 

Ciorba Group was awarded the Work Order having submitted the lowest responsible quotation.

 

As part of this Work Order, the City included the option to utilize the services of the successful firm for future phases.

 

DISCUSSION:

Due to the successful execution of Work Order 22-067C, and in order to maintain project continuity and efficiency, staff recommends the City exercise its ability to retain Ciorba Group for construction engineering and construction observation services for the construction phase of the Ogden Avenue and Washington Street Water Main Improvements.

 

Work Order 22-067-WATER-25-01 includes the following construction engineering services:

                     Preconstruction meeting

                     Shop drawing approval

                     RFI responses

                     Pay requests

                     Change orders

                     Progress meetings

                     Weekly reports

                     Punch list

                     Record drawings

                     Project closeout

 

Work Order 22-067-WATER-25-01 includes the following construction observation services:

                     Full-time construction observation

                     Video recording of existing conditions

                     Material verification and testing

                     Measurement and documentation of contract quantities

                     Daily diary record

                     Daily communication with City

 

The term of the contract is approximately 22 months from the date of award through December 31, 2026.

 

FISCAL IMPACT:

CIP #: WU403 - Ogden & Washington Water Main Improvements

 

The requested award is expensed to the account number listed below. The budget allocates $360,000 for construction engineering services for this project. The award is within the approved budget.

 

Account Number

Fund Description

Budget Amount

41251500-531301

Water Utilities Fund

$3,916,984