File #: 20-227    Version: 1
Type: Procurement Award Status: Passed
File created: 2/11/2020 In control: City Council
On agenda: 3/3/2020 Final action: 3/3/2020
Title: Approve the award of Option Year One to Contract 19-063, Concrete Restoration Services, to Whiteline Construction Inc., Baish Excavating Inc. and Davis Concrete Construction Company for an amount not to exceed $250,000, plus a 5% contingency
Attachments: 1. CIP Page
Related files: 19-220, 21-0201

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Option Year One to Contract 19-063, Concrete Restoration Services, to Whiteline Construction Inc., Baish Excavating Inc. and Davis Concrete Construction Company for an amount not to exceed $250,000, plus a 5% contingency

body

 

DEPARTMENT:                     Department of Public Works

 

SUBMITTED BY:                     Richard Dublinski, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The Department of Public Works (DPW) manages concrete, landscaping and asphalt restoration services at locations throughout the City, primarily resulting from the Public Utilities (Electric and Water) and Public Works system repairs and maintenance projects. Concrete restoration services include replacement of sidewalks, roll curb and gutter, barrier curb and concrete drive aprons. Services also include topsoil and seed installation in areas surrounding newly poured concrete. Contractors must have crews available for work on a monthly basis, at a minimum, or as directed by the City.

 

City Council awarded Contract 19-063 to a shortlist of contractors, Whiteline Construction Inc., Baish Excavating Inc. and Davis Concrete Construction Company, on April 16, 2019, for a one-year term from April 16, 2019 to December 31, 2019, with three, one-year options to extend. The contract was awarded to a shortlist of contractors rather than one to ensure work is completed in a timely manner.

 

DISCUSSION:

During the initial term of the contract, all concrete work was given to the low bidder, Whiteline Construction, because they performed well and completed assigned work in the time requested. In 2019, Whiteline performed restoration services to more than 135 locations. Due to the nature of work, staff recommends the City continue with three vendors under contract to have reassurance work can be performed in a timely manner and reduce the time it takes to restore areas adjacent to residences and businesses. Each vendor agreed to maintain rates and terms provide under current contract.

 

The term of the first option year is April 1, 2020 through December 31, 2020, with three one-year options to renew.

 

FISCAL IMPACT:

CIP #: SC223

 

Concrete restoration services are expensed to the operational service and infrastructure accounts listed below. A total of $199,000 is budgeted for concrete restoration work in 2020. Of this $199,000, $110,000 is budgeted as part of the Alley Improvement Program (SC223) in 2020. Funds will also be used for Water and Electric capital projects as restoration work arises. The requested award is within budget.

 

Account Number

Fund Description

Total Budget Amount

31252400-551502

Road and Bridge Fund

$110,000

31251100-531308

General Fund

$1,798,700

40251300-531308

Electric Utility Fund

$884,000

40251300-551502

Electric Utility Fund

$12,982,000

41251540-531308

Water Utilities Fund

$268,000

41251500-551502

Water Utilities Fund

$23,395,000

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.