File #: 24-0256    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Tabled
File created: 2/27/2024 In control: City Council
On agenda: 3/19/2024 Final action:
Title: Approve the award of Bid 24-005, Sylvan Circle and East Porter Avenue Utility and Roadway Improvements, to Millennium Contracting Co. for an amount not to exceed $4,154,103 plus a 3% contingency

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 24-005, Sylvan Circle and East Porter Avenue Utility and Roadway Improvements, to Millennium Contracting Co. for an amount not to exceed $4,154,103 plus a 3% contingency

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     William J. Novack, Director/City Engineer

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The roadways of Sylvan Circle and East Porter Avenue, from Julian Street to Sylvan Circle, are designated as local streets with speed limits of 25 mph. These roadways are currently two-lane substandard roads with no curb and gutter.  This neighborhood and adjacent properties along Prairie Avenue and White Oak Drive are prone to localized flooding due to the lack of a storm sewer network. The Transportation, Engineering, and Development Business Group (TED) has identified the need to improve Sylvan Circle and East Porter Avenue roadways to meet current City standards.

 

The Water Utilities has also identified the need to upgrade the existing water main and sections of existing sanitary sewer along Sylvan Circle and East Porter Avenue. The existing water main is near end of life and sections of the existing sanitary sewer are requiring replacement. 

 

In February 2023, the City issued Work Order 17-122H to design the necessary improvements to upgrade and loop the water main providing better water flow, pressure, and circulation while also creating a better driving experience for motorists by widening and re-aligning the roadway, installing new pavement, curbs and gutters, and a storm sewer system.

 

In February 2024, TED issued Bid 24-005, Sylvan Circle and East Porter Avenue Utility and Roadway Improvements, to make utility improvements and reconstruct Sylvan Circle and East Porter Avenue, from Julian Street to Sylvan Circle.

 

DISCUSSION:

 

Advertisement Date:

 2/7/2024

Notices Sent:

 471

Opening Date:

 3/1/2024

Planholders:

 30

 

 

Proposals Received:

 6

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

Millennium Contracting, Co.

$4,154,103.00

R.W. Dunteman, Co.

$4,456,335.11

Bolder Contractors

$5,128,559.37

Martam Construction, Inc.

$5,404,118.02

Engineer’s Estimate

$5,733,428.00

A Lamp Concrete Contractors, Inc

$6,238,449.17

H. Linden & Sons Sewer And Water, Inc.

$6,555,242.87

 

Due to Millennium Contracting Co. being significantly lower than other bids and the engineer’s estimates, all vendor references were contacted to ensure the required work can be accomplished. The vendor is also prequalified through IDOT to perform the work required within the contract. Being the lowest responsive and responsible bidder, staff recommends Millennium Contracting Co.

 

The term of the contract is from the date of award through the final completion date of May 15, 2025.

 

FISCAL IMPACT:

CIP #:  SC259

 

Construction work related to the Sylvan Circle and East Porter Avenue Utility and Roadway Improvements (SC259) project is expensed to the Infrastructure accounts listed below. In 2024, a total of $5,566,564 was budgeted for SC259. Of this amount, $5,261,564 was budgeted for construction work and an additional $305,000 was budgeted for design and engineering. The requested award can be accommodated within the total project budget. 

 

Account Number

Fund Description

Total Budget Amount

30282200-551502

Capital Projects Fund

$29,448,000

41252000-551502

Water Capital Fund

$40,264,902

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.