File #: 24-0378    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 3/28/2024 In control: City Council
On agenda: 4/16/2024 Final action: 4/16/2024
Title: Approve the award of Bid 24-012, 2024 Sidewalk and Curb Maintenance Program, to IAP Construction Inc., for an amount not to exceed $1,052,280.00, plus a 3% contingency (Item 1 of 2)
Related files: 24-0379

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 24-012, 2024 Sidewalk and Curb Maintenance Program, to IAP Construction Inc., for an amount not to exceed $1,052,280.00, plus a 3% contingency (Item 1 of 2)

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     William J. Novack, P.E., Director of Transportation, Engineering and Development/City Engineer

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The other related item on the City Council agenda is:

                     24-0379 Pass the ordinance approving the 2024 Sidewalk Removal and Replacement Property Owner’s Cost Sharing Program (Item 2 of 2)

 

The Transportation, Engineering and Development (TED) Business Group is responsible for the maintenance of the City’s sidewalk system. The Street Maintenance Improvement Program (MIP) includes projects to maintain roadways and the adjacent pedestrian network. These projects offer a programmatic approach to ensure the City is improving safety concerns and in compliance with ADA standards. Additionally, the City repairs sidewalks on a complaint-driven basis for all properties each year. Repairs are performed to reduce long-term maintenance costs and limit exposure to claims against the City.

 

In March 2024, TED issued Bid 24-012, 2024 Sidewalk and Curb Maintenance Program, seeking a contractor to complete repairs and replacement of various sidewalks, driveways, curbs, and structure conditions that have met established criteria for replacement. In total, over 700 locations were found to require improvements to be made through this project.

 

DISCUSSION:

 

Advertisement Date:

 3/11/2024

Notices Sent:

 259

Opening Date:

 3/29/2024

Planholders:

 21

 

 

Proposals Received:

 7

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

Engineer’s Estimate

$1,446,760.00

IAP Construction Inc.

$1,052,280.00

Strada Construction Co.

$1,180,303.50

Schroeder & Schroeder, Inc.

$1,474,700.00

Whiteline Construction

$1,496,275.00

Everlast Blacktop, Inc.

$1,497,972.50

Davis Concrete Construction Co.

$1,726,184.00

Globe Construction, Inc.

$1,887,632.50

 

IAP Construction is the low bidder and is recommended for the award.

 

The final completion date of this project is May 31, 2025.

 

FISCAL IMPACT:

CIP #:  MP004, MP009, Various Utility projects

 

Sidewalk and curb maintenance work is expensed to the Infrastructure and Operational Services accounts listed below. In 2024, TED included $945,000 in the budget for MP004, the Sidewalk and Curb Replacement Program. Additionally, $13,000,000 was included in the budget for MP009, the Street Maintenance Improvement Program, which includes concrete work that is identified as a part of the program. Staff also identifies areas where concrete repairs are needed following work done by the utilities. As a result, money is included in both the operating and capital budgets for these repairs. The requested award can be accommodated within the budget.

 

Account Number

Fund Description

Total Budget Amount

 30282200-551502

Capital Projects Fund

$29,448,000

41252000-551502

Water Capital Fund

$40,264,902

41251540-531308

Water Utility Fund

$278,000

40251300-551502

Electric Utility Fund

$15,179,200

31251100-531308

General Fund

$2,164,956

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.