Title: Approve the award of Option Year #1 to Contract 22–287, Land Mobile Radio Consultant Services, to TUSA Consulting Services for an amount not to exceed $42,550
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY MANAGER AUTHORITY PROCUREMENT AWARDS

ACTION REQUESTED:
title
Approve the award of Option Year #1 to Contract 22–287, Land Mobile Radio Consultant Services, to TUSA Consulting Services for an amount not to exceed $42,550
body

DEPARTMENT: Police Department

SUBMITTED BY: Jason Arres, Police Chief
N/A
BACKGROUND:
The City Council awarded Contract 22-287 to TUSA Consultant Services on January 17, 2023 for a three-year term from January 20, 2023, to January 19, 2026, with two one-year options to extend.

The purpose of this contract was to hire experienced and qualified independent consultants to partner with the City to provide direction, analysis, designs and recommendations for upgrading the public safety radio system to a P25 standards network.

The City Council awarded Change Order #1 on Contract 22-287 to TUSA Consultant Services on June 11, 2024, for an amount not to exceed $162,800 and a total award of $357,420.

The purpose of that Change Order was for additional support during the P25 Radio Project implementation phase to ensure the system and scope were properly implemented, tested, and expanded to include:

Engagement in the Detailed Design review with Motorola
18 Months Technical Support (includes one multi-day visit every month)
Radio System Staging Support
Microwave Staging Support
Double the hours for Coverage testing and Functional Testing.

The City Council awarded Change Order #2 on Contract 22-287 to TUSA Consultant Services on December 2, 2025, for an amount not to exceed $44,250 and a total award of $401,670.

The purpose of that Change Order was to extend TUSA’s services because of project delays that extended beyond the original 18-month implementation schedule to June 2026.

DISCUSSION:
During the original term of the contract, TUSA performed crucial assistance preparing to go live with this project and their support is still needed because implementation continues with Motorola since final milestones haven’t been completed.